Operations · Sinaloa, Mexico
El Gallo
El Gallo is a gold and silver mine in Sinaloa, Mexico, coming back into production

Gold and silverCopper

Sinaloa, Mexico
Construction began in September 2026
McEwen secured the key permit for the El Gallo mine in December 2025.
Production is targeted for the second half of 2027
Phase 1 is expected to operate for at least 10 years, producing approximately 20,000 GEO a year once commercial production is achieved. A second phase targets 40,000-50,000 GEO a year.
Q2 2026 results, Aug 5, 2026. Forward-looking; see the cautionary statement.
Resources
| Deposit | Category | Grade | Contained |
|---|---|---|---|
| Gold | Measured and Indicated | 0.42 g/t | 199,000 oz |
| Gold | Inferred | 0.41 g/t | 4,000 oz |
| Silver | Measured and Indicated | 42 g/t | 20.1 million oz |
| Silver | Inferred | 33 g/t | 0.3 million oz |
As of Dec 31, 2025 (S-K 1300): McEwen’s Reserves and Resources page.
Qualified persons: Channa Kumarage, P.Eng., Vice President, Operations (technical contents, including reserves) and Luke Willis, P.Geo., Director of Resource Modelling (resources), both Qualified Persons as defined by SEC S-K 1300 and NI 43-101 (presentation, Sept 2026, slide 2). Resources are exclusive of reserves. See the cautionary statement.



Photos: McEwen Inc.